Item Coversheet
City of Bainbridge Island
City Council Agenda Bill
 
PROCESS INFORMATION
Subject: Fletcher Landing Road-End Improvements Construction Award, AB 14-173 - Public Works (Pg. 282)Date: 5/24/2016
Agenda Item: CONSENT AGENDABill No.: 14-173
Proposed By: Public Works Director Barry LovelessReferrals(s):  
BUDGET INFORMATION
Department: Public WorksFund: Road-Ends Improvements CIP
Expenditure Req: $68,936.18Budgeted? YesBudget Amend. Req? No 

REFERRALS/REVIEW
Study Session:  5/10/2016
Recommendation:    Forward to May 24, 2016 consent agenda.
City Manager:  YesLegal:   YesFinance: Yes 
DESCRIPTION/BACKGROUND
Action Item:
Consider approval of the Fletcher Landing Road-End Improvements project construction award.

Background:
This project provides for removal of existing concrete bulkhead and construction of rockery shoreline stabilization including beach access, planting, and other miscellaneous items.

Bids were solicited through the local newspapers and the bid opening was held on Friday, April 29, 2016. The apparent low bidder is Sealevel Bulkhead Builders in the base bid amount of $68,936.18. The engineer’s estimate is $65,000 to $80,000. See attached bid form.


RECOMMENDED ACTION/MOTION
Motion:
I move that the City Council approve the Fletcher Landing Road-End Improvements project construction award to Sealevel Bulkhead Builders in the base bid amount of $68,936.18.
ATTACHMENTS:
DescriptionType
Fletcher Landing Bid FormBackup Material
Fletcher Landing ContractBackup Material