Item Coversheet
City of Bainbridge Island
City Council Agenda Bill
 
PROCESS INFORMATION
Subject: 8:45 PM Core 40 - Miller and Fletcher Bay Road Shoulder Improvements Contract Award, AB 16-145 – Public Works (Pg. 56)Date: 7/10/2018
Agenda Item: UNFINISHED BUSINESSBill No.: 16-145
Proposed By: Public Works Director Barry LovelessReferrals(s):  
BUDGET INFORMATION
Department: Public WorksFund: CIP Non-Motorized
Expenditure Req: $TBDBudgeted? YesBudget Amend. Req? Yes 

REFERRALS/REVIEW
Business Meeting:  6/26/2018
Recommendation:    Forward to July 10, 2018 unfinished business agenda.
City Manager:  YesLegal:   YesFinance: Yes 
DESCRIPTION/BACKGROUND

As last discussed by the City Council at its June 26, 2018, meeting, this Core 40 Program work includes installation of six-foot (5’-paved) road shoulder improvements. Work on Miller Road is from Tolo Road to Peterson Hill Road. Work on Fletcher Bay Road is from High School Road to New Brooklyn Road. The City of Bainbridge Island Core 40 Program was developed in 2007 with the intent of creating a 40-mile integrated shoulder network for bicycles island-wide.

Bids were solicited through area newspapers and the City’s bids and awards listserv. The bid opening was held on June 22, 2018. The only bidder is Titan Earthwork in the amount of $1,376,058.78. See attached bid form for results.

Additional funds in the amount of $47,000.00 are needed for contingency funds and awarding the contract. Upon City Council approval, a proposed budget amendment will be included in the 2nd quarter budget reporting. Staff has reviewed the bid documentation and contractor’s qualifications and recommends that the Council award this contract to Titan Earthwork.

For more information, please visit the project webpage at: https://www.bainbridgewa.gov/216/City-Projects

 



RECOMMENDED ACTION/MOTION

I move to award the contract for the Core 40 Miller and Fletcher Bay Shoulder Improvements Project to Titan Earthwork in the amount of $1,376.058.78, as well as to authorize an associated budget amendment in the amount of $47,000.00 from the General Fund, thereby increasing the spending authority for this project.

ATTACHMENTS:
DescriptionType
CIP Summary PageBackup Material
Core 40 Miller Fletcher Bay Shoulder Imp ContractBackup Material
Core 40 Miller Fletcher Bay Shoulder Imp Bid FormBackup Material
Engineeer's Estimate and Bid TabulationsBackup Material